Solution
Let Abdul Hadi take x days to finish the work alone.
Then Abdullah takes x+10 days.
Work rates:
x1,x+101
Together they finish in 12 days:
x1+x+101=121
Multiply by 12x(x+10):
12(x+10)+12x=x(x+10)
24x+120=x2+10x
x2−14x−120=0
(x−20)(x+6)=0
Reject x=−6.
x=20
Abdul Hadi would take 20 days.